Zero by 2050 is coming closer with hybrid steam boilers
To achieve zero emissions by 2050 – step by step, with the first milestone of halving emissions by 2030 – we installed two hybrid steam boilers, each with a capacity of 15 T/h, for this sugar manufacturer. The project was realized through an intensive collaboration between Callens and Callens-Vyncke.
Technical Specifications
Capacity
2 x 15 T/h
Design pressure
13 barg
Fuel
bi-fuel + electricity
Balance of plant
high pressure 139 barg
Hybrid steam boilers with complete balance of plant
In this initial renewal phase, the two hybrid steam boilers replace the outdated cogeneration system, which relied on an inefficient steam boiler. Now, both electricity and gas can serve as energy sources for these powerhouses. The client selects the optimal option based on availability and prices.
Our project speed is driven by rigorous project management, thorough preparation and maximum use of prefabrication
Kris Stappers
Sales Director Callens Group
Kris Stappers is Chief Sales Officer at the Callens Group. Engineer by training and with extensive commercial experience under his belt, Kris focuses on the intersection of technology and business.
As CSO, Kris now steers the Callens Group’s commercial course. He works closely with managers and technical decision-makers to translate complex energy-related issues into future-oriented solutions.
Because of his background, Kris has a thorough grasp of both the technical reality production environments face and of the strategic objectives organizations pursue. He thinks along pragmatically, poses the right questions and fosters long-term collaborations.
We meticulously executed the balance of plant, including:
Condensate tanks: 2 x 130,000 liters
Hot water tank: 350,000 liters
Degassers: 1x 33 t/h and 1x 125 t/h
Impressive piping exceeding 1,000 meters
Beet harvest speeds up the launch
To make the most of the sugar beet harvest starting in September, we completed the installation by that time – in a record pace of just eleven months. Thanks to through rigorous project management, solid preparation, and as much prefabrication as possible, we made it happen. For instance, we prepared over 1,000 meters of pipes in our own workshop.